Central Avenue – Accelerated Bridge Construction


Location: Fort Erie, ON
Client:
Rankin
Duration: 2015-2016
Key Staff: Wade Pottie


Project Description

A crane lifts a portion of the old Central Avenue bridge during deconstruction.

The central avenue replacement bridge will replace an existing 5 span bridge structure. The existing bridge longest span is a through truss design that spans 61.56m over 4 railroad tracks. Due to the location of existing adjacent properties, the new bridge was designed to be located in the same footprint as the existing bridge (with longitudinally offset foundations so that the new foundations can be constructed beneath the existing bridge while it was still in service).

The new bridge is a 3 span continuous (35m, 46.5m, 33.2m), variable depth, plate girder bridge with composite 250mm thick concrete deck skewed at 12 degrees and supported on shallow reinforced concrete abutments and piers complete with spread footings founded on bedrock. The 250mm thick concrete deck has a total width of 14.4m and was designed to support 2 – 3.5m traffic lanes, 2 – 1.5m wide bike lanes and 2 – 1.8m wide raised concrete sidewalks. The center span of the new bridge spans over 4 existing railroad tracks.

Due to the importance of the existing thoroughfare, an accelerated bridge construction scheme that includes constructing the new bridge superstructure on temporary bents adjacent to the existing bridge structure and then transversely launching the bridge into its final position during a full road closure was the option selected by the bridge owners (Regional Municipality of Niagara). The total transverse launch distance from the superstructure temporary location into final position was 14.63m.


Harbourside’s Role

Harbourside was responsible for the structural design of the 4 – self stabilizing temporary steel bents which were supported on spread reinforced concrete footings founded on bedrock. The bents were designed to support the entire superstructure dead loads (i.e. steel girders, concrete deck, concrete sidewalks, concrete barriers, steel railings), along with construction wind loads and thermal movements.

Unique Challenges

With 11,300 daily vehicles crossing the bridge, it was important to ensure traffic disruptions were kept to a minimum. As such, Rapid Bridge Construction techniques were used to erect the bridge within an 8-hour time frame.

Social Impact

The completed bridge features 2 lanes for traffic, two bike lanes, and sidewalks. These features go a long way into increasing the accessible transportation options available to the residents of Fort Erie. As its name implies, the central avenue bridge is centrally located, making it an incredibly important roadway. This promising new structure replaces its 50-year-old predecessor, with a design that will allow for future CN/CP rail expansion.

Previous
Previous

THE BIG LIFT: Angus L. MacDonald Redecking Project

Next
Next

Seal Island Bridge Emergency Repair