Rocky Barachois Bridge Replacement Approach 


Location: Gros Morne, NL, Canada
Client: Parks Canada
Duration: 2016
Key Staff: Michael MacDonald, Todd Menzies, Wade Pottie


Project Description

In 2016, Gros Morne continued its series of bridge replacement projects. This time, the focus was on the Rocky Barachois Bridge. Once again, Harbourside was contracted to provide detailed concept, design, and tender documents.

A panoramic view of the old Rocky Barachois bridge in winter. Snow can be seen on the mountains in the background. The outdated bridge structure would be replaced by Harbourside by 2016, necessitating a new highway approach.

Harbourside’s Role

Harbourside Transportation Consultants completed the design of the vertical and horizontal alignments, from initial concept layouts through to detailed design and tender for the new approaches to the Rocky Barachois Bridge Replacement.

Harbourside Geotechnical Consultants conducted an investigation of the approaches at this site. This investigation indicated that constructing the new bridge beside the existing, while maintaining two lanes of traffic on the existing bridge required significant infilling and rework of the approaches. Options considered the use of a two-lane detour structure positioned either east or west of the existing alignment to allow the new bridge construction along the existing alignment.

This investigation also indicated that less fills would be required with the detour structure positioned east of the existing bridge. Based on this, three highway horizontal alignments were considered: matching the existing, shifting the alignment east (7,045 mm offset) so that it partially overlapped the existing structure, and shifting the alignment east to be clear of the existing structure. Constructing the new bridge partially in the footprint of the existing bridge helps to minimize the amount of infilling on the approaches. Design of the new bridge was undertaken by Harbourside Engineering Consultants , making this project a truly comprehensive endeavour for the group, start to finish. The bridge was erected via crane lift, using advanced bridge building methodology.

Different phasing/detour options were considered to maintain two lanes of traffic throughout construction. For completeness and in the interest of reducing the overall project cost, an option was developed which maintained a single alternating lane of traffic throughout construction. The third highway alignment option considered the new bridge constructed adjacent to the existing bridge with a minimum of 900 mm clearance between the new and existing structures. This option presented the simplest option from a construction phasing perspective as well as removes the demolition of the existing structure from the critical path.

The vertical alignment options were investigated for each bridge structure alternative to satisfy the minimum Stopping Sight Distance requirements of TAC and to maintain a clearance box like the existing. The current minimum clearance box is approximately 4,200 mm. The vertical alignments considered resulted in a minor clearance box reduction. The vertical alignment was also optimized to minimize the construction zone length and the overall construction costs.

All alignment work was carried out using appropriate TAC and NLDTW Guidelines and sound engineering design practices. The design minimized the amount of realignment required for the existing highway while providing the highest level of safety and driver comfort as practically possible.

A view of the recently completed Rocky Barachois Bridge in 2016. Harbourside Transportation consultants redesigned the highway approach in order to better accommodate the new structure and its sightlines.

Unique Challenges

Ensuring minimal disruptions to traffic flow during construction was critical to this project. Multiple options were considered before settling on the best solution.  

Social Impact

As part of the redevelopment of the Gros Morne highway and bridge network, the replacement of the Rocky Barachois Bridge is another important step towards modernizing the infrastructure of the area. The new bridge and approaches go a long way in improving safety while traveling along this picturesque roadway.

Previous
Previous

Bakers Brook Bridge Replacement Approach

Next
Next

Maritime Link