Midgell Bridge Replacement


Location: King’s County, PEI
Client: PEI Department of Transportation and Public Works
Duration: 2006
Approximate Value: $5.0 M
Key Staff: Greg MacDonald, Jim Bennett


The former site of Midgell Bridge after demolition. The new bridge is located immediately to the left. Traffic was diverted to the new structure before the old bridge was demolished.

Project Description

While working for another consultant, the Principals of Harbourside Engineering Consultants designed a replacement bridge over the Midgell River. The bridge is located on the busiest highway on Prince Edward Island.


Harbourside’s Role

The bridge is a 60 meter single span, twin trapezoidal box girder structure supported on semi-integral abutments founded on end bearing piles. Harbourside’s deliverables included tender and construction documents for the new bridge as well as for the temporary supports, construction phasing and horizontal launch details.

Accelerated bridge erection techniques were used to transversely slide new bridge in place during a two-day closure.

Placement and alignment of the trapezoidal girder for the new Midgell Bridge replacement circa 2006

The new Midgell Bridge on its permanent abutments as construction finishes. Construction vehicles still on site as the bridge prepares to open to traffic.

Unique Challenges

The project was unique in that the new bridge was built immediately adjacent to the existing bridge and supported on temporary abutments. Traffic was then diverted to the new structure while the existing structure was demolished and new abutments installed. A full closure of the highway was required for only 2 days to allow the new bridge to be horizontally launched onto the permanent abutments and paving of the deck to be completed. This method of construction allowed a very busy highway to remain open, avoided a long, unsuitable off-site detour and eliminated the requirement for a temporary bridge.


Social Impact

For a construction project of this size, an extended closure is typically expected. Completing the replacement in such a reduced time, with minimal highway closures, ensured that this main thoroughfare was kept active, and traffic was impacted as little as possible.

The finished structure of the new Midgell bridge. Demolition of the old bridge is completed, and traffic has been redirected to the new structure.
Previous
Previous

Moriah Bridges Self Launching Bridge Erection